What earthquake-prone means
A building, or part of a building, is earthquake prone if it is likely to collapse and cause injury or death, or damage to another property, in a moderate earthquake. A moderate earthquake would generate a third of the level of shaking used to design a new building at the same site.
Earthquake-prone buildings (EPB) are given an earthquake rating, commonly referred to as a percentage of the new building standard (NBS). Earthquake ratings mean the degree to which the building, or part, meets the seismic performance requirements of the Building Code. Buildings that achieve less than a third of the new building standard (below 34% NBS) are considered earthquake-prone.
The earthquake-prone building process
In May 2016, Parliament amended the Building Act 2004 to introduce a nationally consistent approach to the assessment and management of earthquake-prone buildings, including standardised notices and a national public register. This earthquake-prone building process came into force on 1 July 2017.
The earthquake-prone building process can be summarised in following five steps.
1. Identification
The Council will identify buildings that are potentially earthquake-prone and notify owners.
How territorial authorities identify potentially earthquake-prone buildings – Building Performance
2. Assessment
Owners of potentially earthquake-prone buildings will then provide more information about their building to the Council.
The Council will then confirm whether the building is earthquake-prone or not.
3. Notification
Owners of earthquake-prone buildings will receive confirmation from the Council and will be issued an earthquake-prone building notice with a deadline to strengthen or demolish.
4. Seismic work
Owners of earthquake-prone buildings will then carry out seismic work to ensure that their building is no longer earthquake-prone. This normally involves strengthening, demolishing, or partially demolishing the building.
The timeframe for carrying out seismic work for most buildings in Wellington is 15 years, however, buildings that have been identified as priority buildings have 7.5 years.
5. Removal of the notice
Once the seismic work has been completed and a Code Compliance Certificate (CCC) has been issued, we'll review the work and inform the owner that the building is no longer considered earthquake-prone and the notice can be removed.