Below are Council consents, services and fees that you may need to know about as part of your deck-building project:
Council land
If you want to do any work on or affecting Council land, you will need to get permission first.
If you are not sure whether your land joins on to Council land and/or where the boundaries are, you may need to employ a surveyor or property lawyer to find this information.
The table below outlines a range of options available for the use of Council land.
| If you want to: |
Phone (04) 499 4444 and ask for: |
| Buy Council land |
Property Projects team |
|
Lease Council land
- Legal road
- Reserve land
- Other land
|
- Encroachments team
- Property Management team
- Property Management team
|
| Install services through Council land |
Property Projects team |
| Close the road temporarily |
Roading team |
| Establish access through Council land |
Property Projects team |
| Remove vegetation on Council land |
Customer Liaison Officer, Trees team |
Resource Consent
If your project does not comply with the rules of the District Plan, you will need to apply for resource consent.
To find out if your project complies:
- engage a professional to help you - this could be a planning consultant, architect or draughtsman
- talk to a Council planning technician - phone (04) 801 3590 between 8am and 5pm, Monday to Friday.
| Fees |
Resource Consents - Fees |
| Time frame |
We will process a straightforward consent within 20 working days.
This time frame may be affected if:
- the project is complex
- other parties are affected by the proposal
- the application does not include the right information.
|
| More information |
|
Building Consent
All building works must comply with the Building Act to make sure that they are built safely and to an appropriate standard.
To find out whether your project will require building consent:
| Fees |
Building Consent Fees booklet (295KB PDF) |
| Time frame |
We process building consents within 20 working days.
This time frame may be affected if the application:
- is incomplete
- does not include all the right information.
|
| More information |
Building Consent - Guidelines |