Playground upgrades

Status Closed
Start date 29 November 2018
Closed date 7 December 2018
Number of submissions 175

What happened to this consultation?

We sought and considered public feedback on some draft plans for upgrades in the following playgrounds:

  • Glamorgan Park Playground (Northland)
  • Jeypore Playground (Berhampore)
  • Larsen Park Playground (Tawa)
  • Seatoun Park Playground
  • Taylor Park Playground (Tawa)

Upgrades completed

Glamorgan Park Playground

The upgrade included:

  • Set of swings
  • Basket swing
  • Timber stepping logs
  • Timber stilts
  • Waterlilies balance posts
  • Spinner
  • Main play structure that provides opportunities for climbing and sliding

The upgrade was completed on 22 March 2019 and cost $116,748.08.

Jeypore Playground

The upgrade included:

  • Refurbished swings
  • Main play structure that provides opportunities for climbing and sliding

The upgrade was completed on 31 June 2019 and cost $35,000.00.

Larsen Park Playground

The upgrade included:

  • Set of swings
  • Basket swing
  • Double see-saw
  • Balance beams
  • Steppers
  • A main play structure that provides opportunities for climbing, balancing and sliding

The upgrade was completed on 17 May 2019 and cost $101,807.27.

Seatoun Park Playground

The upgrade included:

  • Set of swings
  • basket swing
  • toddler swing
  • double See-saw
  • min play structure that provides opportunities for climbing, balancing and sliding.

The upgrade was completed on 3 April 2019 and cost $109,547.00.

Taylor Park Playground

The upgrade included:

  • Set of swings
  • Timber climbing cube
  • Double see-saw
  • Main play structure that provides opportunities for climbing and sliding

The upgrade was completed on 15 March 2019 and cost $84,386.08.