These 12 projects / proposals concerning the Courtenay precinct are either underway or being investigated:
| Project | Progress / Timeline |
|---|---|
| May | |
| Proposed Liquor Control Bylaw Amendment |
3 April - 8 May: consultation open 22 May: oral submissions 27 June: Council decision 1 August: Implementation underway |
| Alcohol Accord | May: Key stakeholders meet |
| June | |
| Street lighting upgrade |
Council decision in June; subject to Draft Annual Plan approval in July; work completed by December Other street lighting may be considered in later streetscape design work |
| CCTV surveillance in central city |
Council decision in June; subject to Draft Annual Plan approval in July |
| Late-night taxi management |
Options considered in June |
| July | |
| Walkwise staff | Two additional Walkwise officers; subject to Draft Annual Plan approval in July |
| August | |
| Staffed police kiosk | Recommendations considered by August |
| October / November | |
| Summer concert programme | Applications open pre-Christmas period for licences to trade / busk in Courtenay Place Park |
| December | |
| Peak-time bus priority | December: work completed |
| Courtenay precinct officer | By December: Council considers proposals |
| Heritage toilet building | Request for Proposals for use considered by December (release early 2009) |
| Flexible revitalised streetscape | December: Council considers concept proposal; public consultation likely in 2009 |
Laurie Gabites
Project Manager
| Phone: | (04) 803 8094 |
| Email: | laurie.gabites |